Check out the latest news and articles.
-
Updated floor plan
Posted on May 12, 2017On May 12, an updated floor plan for the building was shared with stakeholders. The plan reflects the project as it stood in late April […]
-
Working toward the 75% design review
Posted on April 27, 2017The architects and the design team are working towards the next big milestone: the 75% design review. A big focus right now is identifying additional […]
-
35% design review updates shared during April 7 teleconference
Posted on April 7, 2017CALS hosted a teleconference on April 7 to share updates on the project. At the time, the project was near the end of the 35% […]
-
35% design review commences
Posted on February 28, 2017The building plans were submitted to the state Division of Facilities Development (DFD) for 35% review on Tuesday, Feb. 28. The DFD’s review is expected to take […]
-
Building exterior approved by UW Design Review Board
Posted on February 21, 2017The concept for the building’s exterior was approved by the UW Design Review Board on Tuesday, Feb. 21. It’s important to note that while the […]
-
Coming up next: the 35% design review
Posted on January 27, 2017Once the design documents (plans and specifications) reach 35% design, they are ready for an extensive review. Here’s what’s involved: Full-size design drawings (along with […]
-
Progress on floor plan
Posted on January 19, 2017On Jan. 19, a current, simplified floor plan for the building was shared with stakeholders. Click here to download the floor plan. The plan will […]
-
Building exterior presented at UW Design Review Board
Posted on December 15, 2016A new architectural concept for the exterior of the building was shared with the UW-Madison’s Design Review Board on December 15. It was the first […]
-
Two industry partners join design team
Posted on December 1, 2016Two industry partners have joined the design team as active members: Lyle Clem, a partner in Electrol Specialties Company, a consulting and equipment design/fabrication firm specializing […]
-
Design team moving forward, anticipated project timeline
Posted onThe design team—which includes representatives from Zimmerman Architectural Studios, the state, UW-Madison, CALS, CDR, the food science department and industry—is meeting weekly and making key […]