Updated images of CDR addition
Posted on April 18, 2018Zimmerman Architectural Studios recently shared the following updated images of the exterior and interior of the CDR facility:
-
Photo: Project leaders with Governor Walker after Building Commission approval
Posted on April 12, 2018On April 11, the funding plan for the CDR/Babcock Hall building project was approved by the state Building Commission. This photo was taken immediately after […]
-
CDR/Babcock Hall building project moving into construction phase
Posted on April 11, 2018The CDR/Babcock Hall building project reached a major milestone: The project’s funding plan was approved by the state Building Commission on April 11 and by […]
-
Bids received for CDR/Babcock Hall building project
Posted on March 27, 2018On March 27, general prime contractors submitted bids to the state Department of Administration for construction of the CDR/Babcock Hall project. These final bids included […]
-
Images of exterior, interior of building
Posted on February 27, 2018Below are updated images of the building project, provided by Zimmerman Architectural Studios. The exterior of the building: The Food Applications Lab:
-
Building project documents out for bid
Posted on February 9, 2018The final 100% design documents were posted for bid on February 9. The documents are online now, being reviewed by potential contractors. As is standard […]
-
Project timeline extended 6-8 weeks to ensure accurate bids
Posted on November 30, 2017The state Department of Administration, UW-Madison campus leaders and the Zimmerman architectural team agreed to extend the project timeline by 6-8 weeks. This will give […]
-
100% design documents completed, being finalized for bidding process
Posted on November 20, 2017The design plans are now in the final phase before the project goes to bid. The state Division of Facilities Development and university representatives recently […]
-
Summer 2017 update
Posted on August 31, 2017The architects and design team spent the summer working toward the building’s 100% design. The 100% design plans are anticipated to be completed by late […]
-
Executive Committee meets, confirms path forward
Posted on May 25, 2017The project’s Executive Committee group met on May 25 to discuss the current state of the project, remaining budget challenges and options to move forward. […]