Chancellor Blank meets with stakeholders, reviews current plans
Chancellor Rebecca Blank addressed a group of stakeholders regarding the Babcock Hall project, thanking them for their past and future involvement and noting the importance […]
-
Posted on September 8, 2016
Value engineering continues
With a total of $11 million in overall costs needing to be cut from the project, the work groups continue to review solutions. The original […]
-
Posted on August 15, 2016
Work continues on design and scope
The smaller working group continues to meet to reconcile changes in square footage and equipment between the original project RFP and the plans as of […]
-
Posted on August 3, 2016
Project stakeholders convene on UW-Madison campus
UW-Madison Interim Vice Chancellor for Finance and Administration Michael Lehman invited key stakeholders to a meeting on Wednesday, Aug 3, 2016 to review options for […]
-
Posted on July 12, 2016
Donors meet with UW leaders
Campaign co-chairs Dave Fuhrmann and Lou Gentine and John Umhoefer met with CALS Dean Kate VandenBosch and UW Foundation President Mike Knetter to discuss the […]
-
Posted on July 8, 2016
Design, budget concerns over UW’s Babcock Hall, CDR project
A story in the July 8, 2016 edition of the Cheese Market News outlined industry concerns about increases in the proposed size and scope of […]
-
Posted on December 15, 2015
Additional private funds raised to expand project
The UW Board of Regents and the State Building Commission have approved a $2.5 million increase in the project budget and the design report. The expanded […]
-
Posted on September 16, 2015
35% design report submitted
The project has passed the important milestone of submitting the 35% design report to the state Division of Facilities Development for necessary approvals. This indicates […]
-
Posted on January 15, 2014
Design begins
The state Division of Facilities Development has approved the design contract with architecture and engineering firm Zimmerman Architectural Studios. This will allow the team to […]
-
Posted on July 1, 2013
Zimmerman Architectural Studios selected as design architect
Zimmerman Architectural Studios has been selected by the state Division of Facilities Development as the architecture and engineering firm contracted to work on the design […]